Follow VivaMore’s Rise

Overall progress at VivaMore is 18% (22 September 2026 report). Follow construction step by step through monthly photos taken from the same viewpoints.

Schedule

What stage is VivaMore at, and when is handover?

18%Overall progress

According to the September 2026 report

  • Foundation100%
  • Structure12%
  • Infrastructure9%

17 months to target handover · March 2028

  1. 12 June 2026

    Groundbreaking ceremony

    Completed
  2. August 2026

    First concrete pour

    Completed
  3. September 2026

    Block A foundation completed

    Completed
  4. October 2026

    Block A structural works

    In progress
  5. March 2028

    Target handover

    Destination
Block A · structural works

Floor-by-floor structural works schedule

SPOINT's planned structural works schedule for Block A: each row shows the planned concrete pour date for that floor's slab. The foundation was complete as of September 2026.

  1. RoofUp next
  2. 12th floorUp next
  3. 11th floorUp next
  4. 10th floorUp next
  5. 9th floorUp next
  6. 8th floorUp next
  7. 7th floorUp next
  8. 6th floorUp next
  9. 5th floorUp next
  10. 4th floorUp next
  11. 3rd floorUp next
  12. 2nd floorUp next
  13. 1st floorUp next
  14. Ground floorUp next
  15. Foundation (raft)Completed
Floor slab
14
The beginning
20 October 2026
Structural works completion
1 April 2027
Average
One floor every ~13 days

Dates are planned; actual progress is shared in the monthly reports. Download the original schedule (PDF, 190 KB)

VivaMore Progress

Monthly Project Progress Reports

Monthly photos from the same viewpoints, work completed and the next step.

Latest report · 22 September 2026

September 2026

As of September 2026, the Block A foundation is complete. Ground was broken on 12 June 2026, with the first concrete pour in August 2026; a raft foundation and C35 concrete were used in accordance with the ground investigation.

  • The first concrete pour took place two months after the groundbreaking ceremony (August 2026)
  • Block A raft foundation concrete completed (C35)
  • Formwork installed for Block A ground-floor columns
  • Site infrastructure: work started on rainwater and drainage lines

Next stepOctober 2026 · Block A first-floor structural works

Read the report — VivaMore Progress · September 2026
  1. September 2026Overall progress 18% ·
  2. October 2026Next report
FAQ

Construction progress FAQs

The questions most frequently asked of the Sales Office on this topic.

What stage has construction reached?

Ground was broken on 12 June 2026; a raft foundation and C35 concrete are being used, and a geotechnical report is available. Monthly progress reports are published on the Construction Progress page.

How can I follow progress?

The Construction Progress page provides a report with photos taken from the same angles every month and updated progress percentages.

How long until handover?

The target handover date and the number of months remaining are shown in the schedule panel on the Construction Progress page; the panel is updated with each monthly report, along with completed stages.

What does the monthly report include?

Each report includes before-and-after photos from the same fixed viewpoints, an aerial view, progress percentages for foundations, structure and infrastructure, work completed that month and the next milestone.

Can't find your question here?

Message the Sales Office; your question will be answered the same day during opening hours.

The company developing VivaMore

SPOINT Construction

Group companies: Leopoint Furniture · Gold Stone

  • 29Completed projects
  • 260,000 m²Total project area
  • 6Countries
About SPOINT Construction
@spoint.vivamoreInstagram

Latest from VivaMore

We share construction progress, events and life at VivaMore on Instagram.

Follow us on Instagram
  • BİRLİKTEN GÜÇ DOĞAR! Güçlü iş birlikleriyle, her detayda aynı kalite anlayışı.
  • BİRLİKTEN GÜÇ DOĞAR! Güçlü iş birlikleriyle, her detayda aynı kalite anlayışı.
  • BİRLİKTEN GÜÇ DOĞAR! Güçlü iş birlikleriyle, her detayda aynı kalite anlayışı.
  • Hayalinizdeki Yaşama Açılan Dijital Kapı!
  • VivaMore’un Web Sitesi Yayında!
  • VivaMore’u keşfetmenin yeni adresi!
  • Milli tenisçi Melis Sezer, Spoint VivaMore TEN-PRO Global Junior Tour Kampı’nda genç sporcularla buluşuyor.🎾 28 Eylül – 3 Ekim tarihleri arasında düzenlenen alt
  • Milli tenisçi Melis Sezer, Spoint VivaMore TEN-PRO Global Junior Tour Kampı’nda genç sporcularla buluşuyor.🎾 28 Eylül – 3 Ekim tarihleri arasında düzenlenen alt
  • Milli tenisçi Melis Sezer, Spoint VivaMore TEN-PRO Global Junior Tour Kampı’nda genç sporcularla buluşuyor.🎾 28 Eylül – 3 Ekim tarihleri arasında düzenlenen alt
  • VivaMore Life; 1+0, 1+1 ve 2+1 farklı daire seçenekleriyle farklı yaşam ihtiyaçlarına uyum sağlayan alternatifler sunuyor.
  • VivaMore Life; 1+0, 1+1 ve 2+1 farklı daire seçenekleriyle farklı yaşam ihtiyaçlarına uyum sağlayan alternatifler sunuyor.
  • VivaMore Life; 1+0, 1+1 ve 2+1 farklı daire seçenekleriyle farklı yaşam ihtiyaçlarına uyum sağlayan alternatifler sunuyor.
Live streamLive from the site