September 2026
As of September 2026, the Block A foundation is complete. Ground was broken on 12 June 2026, with the first concrete pour in August 2026; a raft foundation and C35 concrete were used in accordance with the ground investigation.
- The first concrete pour took place two months after the groundbreaking ceremony (August 2026)
- Block A raft foundation concrete completed (C35)
- Formwork installed for Block A ground-floor columns
- Site infrastructure: work started on rainwater and drainage lines
Next stepOctober 2026 · Block A first-floor structural works