Work completed this month
- The first concrete pour took place two months after the groundbreaking ceremony (August 2026)
- Block A raft foundation concrete completed (C35)
- Formwork installed for Block A ground-floor columns
- Site infrastructure: work started on rainwater and drainage lines
October 2026 targetBlock A first-floor structural works
Site photographs
June 2026 → September 2026 · slide to compare

June 2026September 2026
June 2026September 2026
June 2026August 2026“We have completed the Block A foundation using a raft foundation and C35 concrete in accordance with the ground investigation; the first structural floor will be visible in October.”
Roadmap
- 12 June 2026Groundbreaking ceremony
- August 2026First concrete pour
- September 2026Block A foundation completed
- October 2026Block A first-floor structural works
- 2028Handover